Press-centre
Press releases
LLC «Engineering and Design Center of New Generation» is working on the Kurgan load node reconstruction project
LLC «Engineering and Design Center of New Generation» is working on the Kurgan load node facilities and systems reconstruction projects for OJSC «Kurganenergo». This will increase reliability of the Kurgan power supply.
Administrative and auxiliary blocks are being constructed on the Kurgan CHPP-2 site.
The administrative and auxiliary blocks are being built on the Kurgan CHPP-2 site. At present structural steel installation of both the buildings is being finished.
GT unit and ST unit foundations are completed on the Chelyabinsk CHPP-3 power unit under construction
CJSC «Intertechelectro» is continuing to construct a 220 MW CCGT power unit, Chelyabinsk CHPP-3 (OJSC «Fortum») 3rd power unit.
Bridge crane installation has been launched on the Kurgan CHPP-2
The 1st bridge crane installation has been launched at the Kurgan CHPP-2 turbine building.
MES of Center has launched complete modernization of the 220 kV Rayonnaya substation
MES of Center, branch of OJSC «FSK UES» has launched complete reconstruction of the 220 kV Rayonnaya substation (city of Vladimir).
The 1st Kurgan CHPP-2 project Siemens steam turbine has been delivered to site
The 1st Siemens SST-400 steam turbine for the Kurgan CHPP-2 has been delivered to the site. The 2nd steam turbine delivery is expected by the end of 2009.
Signing of Agreement on appropriation of funds for the Kurgan CHPP-2 thermal capacity output circuit construction
At the International investment forum “Sochi-2009” held in the city of Sochi, on September 19, 2009 there was signed Agreement on appropriation of budgetary outlays from the RF Investment fund and Kurgan region budget resources for implementation of the regional investment project «Kurgan CHPP-2 construction».
The Kurgan CHPP-2 project has been presented at the “Fuel&power sector innovation technologies” exhibition
The “Intertechelectro-New Generation” group of companies took part in the “Fuel&power sector innovation technologies” exhibition held under the VIth Forum of interregional cooperation of the Russian Federation and Republic of Kazakhstan in the city of Orenburg.
Personnel replacements in the «Intertechelectro-New Generation» group of companies.
The «Intertechelectro-New Generation» group of companies is informing of its personnel replacements
Commissioning works are being performed at the 1st power unit of the Noyabrsk CCGT PP
Commissioning works are being fulfilled on the 1st power unit major equipment of the Noyabrsk CCGT PP (YNAO). The 1st power unit steam turbine is put to the hydraulic ratchet pump.
CJSC «Intertechelectro» has started to extend the 220 kV open switchgear of the Chelyabinsk CHPP-3 power unit under construction
CJSC «Intertechelectro» has started to extend the 220 kV open switchgear of the Chelyabinsk CHPP-3 (OJSC «Fortum») 3rd power unit under construction.
Mobile staff meeting on Kurgan CHPP-2 construction has been held
Mobile staff meeting on construction of the Kurgan CHPP-2 has been held in Kurgan.
LLC «EDC-NG» is proceeding to work on the Razdan CHPP power unit #5 modernization
LLC «Engineering & Design center of New Generation» is proceeding to work on the Razdan CHPP power unit #5 modernization project (Republic of Armenia).
CJSC «Intertechelectro» is completing structural steel installation of the Chelyabinsk CHPP-3 power unit under construction
CJSC «Intertechelectro» is completing installation works on the main building structural steel of the Chelyabinsk CHPP-3 (OJSC «Fortum») 3rd power unit– 220 MW CCGT power plant.
The Kurgan CHPP-2 cooling tower is manufactured
At the FANS facilities (city of Hlinsko, Czech Republic) there was manufactured and tested the cooling tower for the Kurgan CHPP-2 under construction. The cooling tower will be shipped to the CHPP site in the near future.
The Kurgan CHPP-2 gas turbines tests are completed
In Belfort (France), at the GE Energy facilities there were conducted the tests of the GE 6FA two gas turbines for the Kurgan CHPP-2 under construction. Such turbines will be installed for the first time in Russia. The inspection revealed complete readiness of the equipment for the site delivery and further operation.
LLC «Service New Generation» presented a new business direction
Within the All-Russia conference “Power industry modernization-2009” the LLC “Service New Generation” presented an innovative business direction on complex maintenance of power industry facilities.
«Intertechelectro-New Generation» group of companies is awarded for the best solution in the project management systems implementation
«Intertechelectro-New Generation» group of companies took a prize in the nomination of «Best implementation of typical solution for construction projects management». The medal ceremony passed under the VIII International conference on project management «PMSOFT and PRIMAVERA - successful investments in industry and construction».
DCS installation is completed at Noyabrsk CCGT power plant
The DCS has been installed at the Noyabrsk CCGT power plant (Yamalo-Nenets autonomous district). It will permit to simplify the plant control and increase its efficiency.
LLC «EDC-NG» is proceeding to work on Razdan CHPP power unit #5 modernization
LLC «Engineering & Design center of New Generation» is proceeding to work on the Razdan CHPP power unit #5 modernization project (Republic of Armenia).