23 August 2016

Czech Export Bank Representatives Visited Kurgan CHPP-2

Representatives of the Czech Export Bank and Insurance Company EGAP paid a working visit of Kurgan CHPP-2.

06 June 2016

LLC “Noyabrsk CCPP” and LLC “Kurgan CHPP-2” topped the Generating Companies Efficiency Rating

LLC “Noyabrsk CCPP” and LLC “Kurgan CHPP-2” topped the Generating Companies Efficiency Rating, which was prepared by the experts of NP “The Market Council”. Noyabrsk CCPP and Kurgan CHPP-2 are acknowledged to be the best in 2015, based on the criterion: “Generating equipment performance efficiency”.  

14 March 2014

Kurgan CHP-2 is recognized as the best infrastructure project in the energy sector

The Kurgan CHP-2 project has been recognized as the best infrastructure project in the energy sector, coming under the notion of “District heating facilities”, within the framework of the “ROSINFRA” National Award procedure for infrastructure-related projects

04 March 2014

A formal ceremony on the occasion of the Kurgan CHP-2 commercial operation commencement was held in Kurgan

A formal ceremony on the occasion of the Kurgan CHP-2 commercial operation commencement (225MW/ 250 Gcal/h) was held in Kurgan on March 4, 2014.

22 October 2013

Kurgan CHP-2 has obtained a certificate of readiness for the autumn-winter season

Kurgan CHP-2 has obtained a certificate of readiness for operation during the 2013-2014 autumn-winter seasons.

15 October 2013

City executives from the Ural Federal District visited Kurgan CHP-2

Within the framework of the Coordination Council session, which was held in Kurgan, members of the “Ural Cities” Association visited Kurgan CHP-2 and familiarized themselves with the project implementation experience.

25 June 2013

Integrated testing of Power Generating Unit No2 at Kurgan CHP-2 has been completed

Integrated testing and certification of the operating capacity of Power Generating Unit No2 at Kurgan CHP-2 has been successfully completed.

11 March 2013

Integrated testing of Power generating unit No1 has been carried out at Kurgan CHP-2

CJSC “Intertechelectro” has successfully conducted integrated testing of the equipment on Power Generating Unit No1 of Kurgan CHP-2.

29 November 2012

A conference, attended by Governor Bogomolov and all the contractors involved was held at Kurgan CHP-2

A conference on the project progress, attended by Governor of the Kurgan region Oleg Bogomolov, was held at Kurgan CHP-2. The conference participants included representatives of the regional government, contractors and equipment suppliers.

07 November 2012

Commissioning of the hot water system at Kurgan CHP-2 has been completed.

An essential stage of the commissioning works has been completed at Kurgan CHP-2: commissioning of the plant hot-water system.

18 September 2012

A scheduled inspection of Kurgan CHP-2 by Rostekhnadzor has been completed

A routine inspection of Kurgan CHP-2 by the Ural Directorate of the Federal Service for Environmental, Technological and Nuclear Supervision, has been completed. The inspection has revealed no serious discrepancies which could impact the power plant commissioning.

05 September 2012

Commissioning works are underway at Kurgan CHP-2

Commissioning of the major equipment is in progress at the power plant. Fired starts of the gas turbine with subsequent no-load running, as well as the waste heat boiler wash-out and trial starts are underway. Siemens is preparing for the steam turbine start.

04 Jule 2012

First firing of a gas turbine carried out at Kurgan CHP-2

The first firing and idle running of a gas turbine has been carried out at Kurgan CHP-2.

30 November 2011

Dmitry Kobylkin, Governor of the Yamalo-Nenetz Autonomous District, visited Kurgan HPP-2

Governor of the Yamalo-Nenetz Autonomous District Dmitry Kobylkin visited the Kurgan HPP-2 construction site, while on a working trip to the Kurgan region.

02 November 2011

Presidential Plenipotentiary Envoy visited Kurgan HPP-2

Presidential Plenipotentiary Envoy to the Ural Federal District Yevgeny Kuyvashev visited the construction site of Kurgan HPP-2.

12 October 2011

A technical conference, attended by Governor of the Kurgan Region, was held at Kurgan HPP-2

A conference on the plant completion, attended by Governor of the Kurgan Region Oleg Bogomolov, was held at the Kurgan HPP-2 site

29 June 2011

Kurgan HPP-2 construction project to be presented to Prime minister Putin

The Kurgan HPP-2 project was presented at the interregional conference “Urals social-economic development strategy up to 2020” and Head of the RF Government Vladimir Putin

18 May 2011

Oleg Bogomolov, Kurgan region Governor, visited Kurgan HPP-2 site

The progress meeting with participation of the Governor and representatives of the Kurgan region government took place at the Kurgan HPP-2site.

25 October 2010

Fume stacks’ installation is in progress at Kurgan HPP-2

Fume stacks’ erection is launched at the Kurgan HPP-2. Totally, the plant will have 3 stacks, 45 meters each.

19 August 2010

Kurgan HPP-2 hot-water boilers have undergone hydraulic testing

The Kurgan HPP-2 hot water boilers have successfully undergone hydraulic testing under supervision of the Rostekhnadzor representatives.