15 Jule 2010

Kurgan HPP-2 fan cooling tower installation is completed

The fan cooling tower sections have been installed at the Kurgan HPP-2. The cooling tower frame, building panels and fans have been mounted within two months

17 June 2010

HRSG installation is launched at Kurgan HPP-2

Installation of the HRSG, one of the most important components of the Kurgan HPP-2, has been started.

14 May 2010

Kurgan HPP– 2 construction project is represented at 1st Russian forum for strategic infrastructure development

Vladimir Babyak, General director of CJSC Intertechelectro, made a presentation of the Kurgan HPP-2 construction project at the 1st international Russian forum for strategic infrastructure development.

05 May 2010

Kurgan HPP-2 fan cooling tower installation is started

Pool concreting is completed and fan cooling tower sections installation is started at the Kurgan HPP-2 site.

16 April 2010

Kurgan region governor took part in gas turbines installation at Kurgan HPP site

The main equipment mounting is going on. On April 16, 2010 the gas turbines were put on the pedestals.

16 April 2010

Kurgan region governor took part in gas turbines installation at Kurgan HPP site

The main equipment mounting is going on. On April 16, 2010 the gas turbines were put on the pedestals.

06 April 2010

Kurgan HPP-2 turbines’ compressors testing is complete

At the ČKD NOVÉ ENERGO plant in Prague (Czech Republic) the gas turbines’ compressors of the Kurgan HPP-2 have been manufactured and tested. In the near future the compressors will be shipped to the site.

04 March 2010

Narkis Galiaskarov provided information on Kurgan HPP-2 construction

Narkis Galiaskarov, executive director of the LLC Kurgan HPP-2, took part in the meeting dedicated to work results of industry, transport, communication and energy companies of the Kurgan region in 2009.

17 February 2010

German Federal Republic delegation visited Kurgan HPP-2 site

Renata Astrid Schimkoreit, general counsel of German Federal Republic in Yekaterinburg, and Hans Jurgen Wio, Siemens-Russia and Central Asia vice-president, have visited the Kurgan HPP-2 site under the German delegation trip to the Kurgan region.

16 February 2010

Major equipment installation is started at Kurgan HPP-2

One of the critical construction steps has been started at the Kurgan HPP-2. Major equipment (gas and steam turbines and water heating boilers) installation will be done in the near future.

10 February 2010

Trans-Urals Enterprises participate in construction of Kurgan CHPP-2

Leading enterprises of Trans-Urals participate in equipment supply and works execution on the Kurgan CHPP-2 site. In particular, OJSC «Kurganhimmash» produced cold water tanks of plate steel for the station needs.

20 January 2010

The 2nd Kurgan CHPP-2 project Siemens steam turbine has been delivered to site

The 2nd Siemens SST-400 steam turbine for the Kurgan CHPP-2 has been delivered to the site. The power plant steam and gas turbines will be installed on foundations in the near future.

16 December 2009

The Kurgan CHPP-2 main building construction is completed.

The Kurgan CHPP-2 main building construction is completed. Heat has been supplied to the building what will allow equipment installing in winter.

15 December 2009

The Kurgan CHPP-2 is acknowledged Investment project of the year.

The Kurgan CHPP-2 construction project is acknowledged «investment project of the year» under Award «Year results of Urals and Siberia– 2009».

27 November 2009

Viktor Basargin, Minister of regional development, visited the Kurgan CHPP-2 site

Viktor Basargin, RF Minister of regional development, visited the Kurgan CHPP-2 site under working trip.

18 November 2009

Administrative and auxiliary blocks are being constructed on the Kurgan CHPP-2 site.

The administrative and auxiliary blocks are being built on the Kurgan CHPP-2 site. At present structural steel installation of both the buildings is being finished.

21 October 2009

Bridge crane installation has been launched on the Kurgan CHPP-2

The 1st bridge crane installation has been launched at the Kurgan CHPP-2 turbine building.

22 September 2009

The 1st Kurgan CHPP-2 project Siemens steam turbine has been delivered to site

The 1st Siemens SST-400 steam turbine for the Kurgan CHPP-2 has been delivered to the site. The 2nd steam turbine delivery is expected by the end of 2009.

21 September 2009

Signing of Agreement on appropriation of funds for the Kurgan CHPP-2 thermal capacity output circuit construction

At the International investment forum “Sochi-2009” held in the city of Sochi, on September 19, 2009 there was signed Agreement on appropriation of budgetary outlays from the RF Investment fund and Kurgan region budget resources for implementation of the regional investment project «Kurgan CHPP-2 construction».

14 September 2009

The Kurgan CHPP-2 project has been presented at the “Fuel&power sector innovation technologies” exhibition

The “Intertechelectro-New Generation” group of companies took part in the “Fuel&power sector innovation technologies” exhibition held under the VIth Forum of interregional cooperation of the Russian Federation and Republic of Kazakhstan in the city of Orenburg.