News

12 September 2016

Scheduled Overhaul Has Been Performed at Noyabrsk CCPP

Scheduled overhaul of the main equipment has been performed on the first power generating unit of Noyabrsk CCPP.  

06 June 2016

LLC “Noyabrsk CCPP” and LLC “Kurgan CHPP-2” topped the Generating Companies Efficiency Rating

LLC “Noyabrsk CCPP” and LLC “Kurgan CHPP-2” topped the Generating Companies Efficiency Rating, which was prepared by the experts of NP “The Market Council”. Noyabrsk CCPP and Kurgan CHPP-2 are acknowledged to be the best in 2015, based on the criterion: “Generating equipment performance efficiency”.  

28 January 2016

Noyabrsk CCPP has passed the power validation test

The System Operator of the United Power System” has approved the results of the scheduled power requalification at Noyabrsk CCPP. The power plant confirmed its capability to carry the maximum electrical load of 124 MW.

22 November 2011

Heads of the Yamal municipalities visited the Noyabrsk CCPP

Eugeny Miskevich, First Deputy Governor of the Yamalo-Nenetz Autonomous District and the Heads of the Yamal municipalities paid a working visit to the Noyabrsk CCPP.

06 October 2011

The Noyabrk CCPP has generated the first billion kW/h

The Noyabrsk Combined Cycle Power Plant (Noyabrsk, the Yamalo-Nenetz Autonomous District) has generated the first billion kWh

15 March 2011

Noyabrsk CCGT PP 3rd power unit construction is possible

The meeting on reforming of the Noyabrsk housing complex under the chairmanship of Dmitry Kobylkin, YNAD governor, involved discussion of prospects of construction of the Noyabrsk CCGT PP 3rd unit

26 November 2010

«Intertechelectro-New Generation» put Noyabrsk CCGT PP into operation

Formal putting into operation of the Noyabrsk CCGT PP (122 MW and 95 Gcal/h) took place on November 19, 2010 in Noyabrsk.

12 August 2010

Noyabrsk CCGT PP 2nd unit has been successfully tested

The Noyabrsk (YNAD) CCGT PP 2nd unit equipment comprehensive testing and working capacity approval has been successfully conducted.

22 June 2010

Dmitry Kobylkin, YNAD governor, has visited Noyabrsk CCGT power plant

Dmitry Kobylkin, Governor of the Yamal-Nenets autonomous district, under the working trip has visited the Noyabrsk CCGT PP.

07 June 2010

Noyabrsk CCGT PP 1st power unit has passed comprehensive testing

The 1st power unit has successfully passed comprehensive testing at the Noyabrsk CCGT power plant (YNAD).

30 April 2010

Noyabrsk CCGT PP gas turbine generator trial launch

According to the electric testing program, the 1st power unit GT generator was connected to the mains under commissioning works.

28 April 2010

Noyabrsk CCGT PP turbine trial launch

The 1st power unit GT trial firing achieving idle stroke was conducted.

13 January 2010

Power unit for the Noyabrsk CCGT power plant is approved

Supervisory Board of the non-profit partnership «Market board» has approved power unit monthly feasible payment for the Noyabrsk CCGT PP for year 2010. The station power 1 MW will cost 820,000.00 rubles per month. All the Noyabrsk CCGT PP output will be sold on wholesale electricity and capacity market (WECM).

28 August 2009

Commissioning works are being performed at the 1st power unit of the Noyabrsk CCGT PP

Commissioning works are being fulfilled on the 1st power unit major equipment of the Noyabrsk CCGT PP (YNAO). The 1st power unit steam turbine is put to the hydraulic ratchet pump.

01 June 2009

DCS installation is completed at Noyabrsk CCGT power plant

The DCS has been installed at the Noyabrsk CCGT power plant (Yamalo-Nenets autonomous district). It will permit to simplify the plant control and increase its efficiency.

23 April 2009

General Electric experts are training Noyabrsk CCGT power plant personnel

The engineering staff of the Noyabrsk CCGT power plant (Yamalo-Nenets autonomous district) undergoes special training on General Electric MARK VI. The knowledge the employees get will help them to create programs for the equipment control and its further operation.

24 March 2009

New generation turbo-generator is installed at Noyabrsk CCGT power plant

The 25 MW TTK-25 turbo-generator erection has been completed in the main building of the Noyabrsk CCGT power plant (Yamalo-Nenets autonomous district). The Noyabrsk CCGT power plant has become the first power facility in Russia where such a turbo-generator was installed.

04 March 2009

The auxliaries are energized at the Noyabrsk CCGT power plant

The auxiliaries are energized at the Noyabrsk CCGT power plant site. The energization is intended for commissioning works of the 62 MW power unit #1 and common plant equipment

18 February 2009

The Noyabrsk CCGT power plant is hiring operating personnel

Operation of the 124 MW Noyabrsk CCGT power plant (Yamalo-Nenets autonomous district) will be done by the operating and engineering staff of the «Service New Generation» (member of the «Intertechelectro-New Generation» group of companies). The Noyabrsk CCGT PP will be staffed completely by March 01, 2009.