News

13 August 2009

Mobile staff meeting on Kurgan CHPP-2 construction has been held

Mobile staff meeting on construction of the Kurgan CHPP-2 has been held in Kurgan.

15 Jule 2009

The Kurgan CHPP-2 cooling tower is manufactured

At the FANS facilities (city of Hlinsko, Czech Republic) there was manufactured and tested the cooling tower for the Kurgan CHPP-2 under construction. The cooling tower will be shipped to the CHPP site in the near future.

23 June 2009

The Kurgan CHPP-2 gas turbines tests are completed

In Belfort (France), at the GE Energy facilities there were conducted the tests of the GE 6FA two gas turbines for the Kurgan CHPP-2 under construction. Such turbines will be installed for the first time in Russia. The inspection revealed complete readiness of the equipment for the site delivery and further operation.

03 April 2008

Kurgan HPP and Czech Export Bank signed a Mandatory Agreement with the basic provisions for granting a loan on the Kurgan HPP-2 construction

Having signed the mandatory Agreement, the Parties settled the agreements on granting a loan for the HPP construction in the city of Kurgan.

26 February 2008

The agreement on the delivery of gas turbines for Kurgan HPP-2 signed

The agreement on delivery of two General Electric gas turbines for Kurgan HPP-2 was signed between Kurgan HPP LLC and PSG-International, the ЕРС contractor for the plant construction.

29 January 2008

The agreement on delivery of the second steam turbine for Kurgan HPP-2 signed

The agreement on delivery of the second power generating steam turbine unit produced by Siemens for Kurgan HPP-2 was signed between Kurgan HPP LLC, a subsidiary of Intertechelectro – New Generation LLC, and PSG-International, the ЕРС contractor for the plant construction.

29 December 2007

Operating results of the Kurgan HPP-2 construction in 2007 announced

During the briefing held today in Kurgan HPP-2 LLC office the Intertechelectro – New Generation Group operating results related to construction of a new HPP have been announced.

04 December 2007

The first contract for delivery of major equipment for Kurgan HPP-2 signed

The contract with Siemens for delivery of a steam turbine for Kurgan HPP–2 was signed in November by PSG–International in Brno (Czech Republic).

31 October 2007

<nobr>Intertechelectro-New</nobr> Generation LLC Held Negotiations with <nobr>PSG-International</nobr> concerning Equipment Supplies to Kurgan <nobr>HPP-2</nobr>

Steam turbine units manufactured by Siemens will be installed at Kurgan HPP-2 that is erected by Intertechelectro-New Generation Group of Companies.

12 October 2007

<nobr>Intertechelectro-New</nobr> Generation LLC Plans to Dispose of Carbon Assets under Kurgan <nobr>HPP-2</nobr> Construction Project

The construction of Kurgan HPP-2 based on advanced technology will permit Intertechelectro-New Generation in cooperation with Camco International to dispose of 880 thousand tons of CO2 under Kyoto Protocol.

26 September 2007

First Pile Has Been Driven into Foundations of Main Building of Kurgan <nobr>HPP-2.</nobr> <nobr>Intertechelectro-New</nobr> Generation Group of Companies Officially Started Construction of New Thermal Power Station

A combined cycle thermal power station (222 MW and 250 GCal) will cover a power deficit in Kurgan Region by more than 40% and will make a great push for the regional economy development.

26 September 2007

<nobr>Intertechelectro-New</nobr> Generation LLC and <nobr>PSG-International</nobr> Signed Contract for Design, Supply and Construction of CCGP at Kurgan on September 26, 2007

PSG- International will operate as the EPC Contractor for Kurgan HPP-2 Construction Project, i.e. will ensure turnkey construction of a combined cycle generation plant.

06 September 2007

Kurgan <nobr>HPP-2</nobr> Construction Operations Are Under Way on Schedule

On September 6, 2007, a briefing was held, where Oleg Selvanov, Deputy Director General of Intertechelectro-New Generation LLC, Kurgan HPP-2 Project Manager, explained the progress of work at the project.

21 August 2007

<nobr>Intertechelectro-New</nobr> Generation Company Started Onsite Excavation at Kurgan <nobr>HPP-2</nobr>

Intertechelectro-New Generation LLC started onsite excavation at Kurgan HPP-2, i.e. site grading with reference to established zero elevation.

07 August 2007

Kurgan <nobr>HPP-2</nobr> Construction Site Prepares for Construction Start

Pre-construction operations are carried out at the construction site of Kurgan HPP-2 preceding the principal construction stage.

01 August 2007

Kurgan HPP-2 Construction Site Prepares for Construction Start

Pre-construction operations are carried out at the construction site of Kurgan HPP-2 preceding the principal construction stage.

20 June 2007

Oleg Bogomolov Referred to Signature of Agreement with <nobr>Intertechelectro-New</nobr> Generation LLC as Important Step towards Avoidance of Energy Deficit in Kurgan Region

Head of Kurgan Region made such a statement at a press conference held by Oleg Bogomolov and Artem Bikov, Chairman of the Board of Directors for Intertechelectro-New Generation LLC just following the completion of a ceremony of signing the agreement on cooperation and interaction in developing and implementing an investment program for a new generation construction project in Kurgan Region.

20 June 2007

Agreement for Future

An agreement on cooperation and interaction in developing and implementing an investment program for a new generation construction project in the territory of Kurgan Region has been signed between the Government of Kurgan Region and Intertechelectro-New Generation LLC.

28 May 2007

Construction of Kurgan (Northern) <nobr>HPP-2</nobr> as Outcome of Reforms in Russian Energy Industry

Anatoly Bondarev, Deputy Governor of Kurgan Region, Head of Regional Energy Program Agency, referred to the construction of Kurgan HPP-2 (Northern HPP) at the Town of Kurgan as a strategically important task.

11 May 2007

<nobr>Intertechelectro-New</nobr> Generation LLC Kurgan <nobr>HPP-2</nobr> Construction Project Has Been Made Part of Agreement Signed by Administration for Kurgan Region and OJSC UES Russia

An Agreement for Interaction towards implementation of energy companies’ activities to ensure reliable power supplies and make provisions for connection to power grids of consumers from Kurgan Region has been signed this day between the Administration of Kurgan Region and OJSC RAO UES Russia involving Intertechelectro-New Generation LLC. Alexander Kogan, Director General of Intertechelectro-New Generation LLC, took part in the ceremony of signing the Agreement.