21 November 2008

Russian engineering companies have consolidated into National association

The engineering services market companies has established the first professional association. The Non-profit institution «National association of engineering companies» (NAEC) is declared to have been organized in Moscow. Artyom Bikov, Chairman of the Board of Directors of LLC «Intertechelectro-New Generation» is elected its President.

20 November 2008

LLC «Service New Generation» is getting prepared for the Noyabrsk CCGT PP DCS installation and gas turbines operation

The operation and maintenance company «Service New Generation», member of the «Intertechelectro-New Generation» group of companies, has supplied the DCS equipment to the 124 MW Noyabrsk CCGT PP in Yamal-Nenets autonomous district.

13 November 2008

«Intertechelectro-New Generation» group of companies celebrates the World quality day

The «Intertechelectro-New Generation» group of companies joins the celebration of the World quality day and congratulates all the specialists dealing with quality issues at its enterprises.

31 October 2008

Heat is supplied to the Noyabrsk CCGT PP Main building

The Noyabrsk CCGT PP (Yamal-Nenets autonomous district) main building has now the heating devices installed what allowed supplying heat to the building at the end of October.

30 October 2008

LLC «PEC-NG» is preparing modernization of the Razdanskaya CHPP power unit №5

LLC «PEC-NG» will fulfill the whole design scope under modernization of the Razdanskaya CHPP power unit №5 (Republic of Armenia) with the gas turbine built over. The relevant agreement has been signed by Karen Sargsyan, director of «Razdan-5» of CJSC «ArmRosgazprom, and Georgiy Fedorin, General director of LLC «PEC-NG».

24 October 2008

LLC «PEC-NG» and AVEVA develop cooperation

LLC «Project & engineering center of New Generation» extends cooperation with AVEVA. 8 designers more of the Moscow office of LLC «PEC-NG» have been trained in AVEVA on working with the 3D modeling software. At present, the parties are negotiating on purchase of new licenses for the product application.

14 October 2008

The first steam turbine installation works have been launched at the Noyabrsk CCGT PP

The installation works on the first steam turbine have been launched in the main building of the Noyabrsk CCGT PP (Yamal-Nenets autonomous district). In accordance with the schedule, the second steam turbine installation will start one month and a half later.

08 October 2008

Integrated switchgear has been installed at the Noyabrsk CCGT PP

At the Noyabrsk CCGT PP constructed by the «Intertechelectro-New Generation» group of companies the Siemens SF6 complex switchgear has been installed.

03 October 2008

CJSC “Intertechelectro» has received the «EnCERTICO” certificates

CJSC «Intertechelectro» (engineering and construction company, member of the «Intertechelectro-New Generation» group of companies) certified its services in “EnCERTICO”, power industry facultative certification system.

26 September 2008

CJSC «Intertechelectro» completes the foundations for the Chelyabinsk CHPP-3 3rd power unit frame

At the OJSC “TGK-10” Chelyabinsk CHPP-3 new CCGT power unit construction site the foundation works for the extended part of the main building are being completed. CJSC «Intertechelectro», the general contractor, is getting prepared to move the back wall.

25 September 2008

110/35/6 kV substation “Bereg” commissioning ceremony has been conducted

In Perm the ceremony on the «Bereg» substation with 110/35/6 KW commissioning has been conducted. CJSC «Intertechelectro» as General Contractor has implemented the construction of substation (the company is a company of Group of the Companies «Intertechelectro-New Generation».

24 September 2008

CJSC «Intertechelectro» puts the substation «Bereg» into operation in Perm

The Engineering Construction Company «Intertechelectro-New Generation» which is a Company of Group of Companies «Intertechelectro-New Generation» has completed the construction and put the «Bereg» substation with 110/35/6 KW into operation in Perm.

08 September 2008

LLC «Service New Generation» will implement automated process control systems (ACS) at the Noyabrsk CCGT PP

LLC «Service New Generation» which is a company of Group of Companies «Intertechelectro-New Generation» has introduced the automatic process control systems and is going to carry out the commissioning works of Noyabrsk CCGT PP (YaNAD).

28 August 2008

Staff meeting on the Noyabrsk CCGT PP construction has been conducted

There was a staff meeting on Noyabrsk CCGT PP construction whish will be the largest one in Yamolo Nenetz Autonomous District. The project realized by Group of Companies «Intertechelectro-New Generation» is at the key stage: the specialists are mounting the main and auxiliary equipment

27 August 2008

CJSC «Intertechelectro» will build in Udmurtia the substation “Zenitnaya” 2nd launch complex

The engineering construction company which is a company of Group of Companies «Intertechelectro-New Generation» was a winner in the JSC «MRSK Center and Volga Region» tender on the construction of the second start-up facilities for «Zenitnaya» substation with 110/6 in Izhevsk. The large grid facility is being built by the order of subsidiary JSC «MPCK Center and Volga Region» «Udmurtenergo».

20 August 2008

Lev Osika presented a unique book on the up-to-the-date experience investment project management in the power industry

Lev Osika, PhD (engineering), presented his book “Investment project management for thermal power plant construction. Pre-investment phase” at the headquarters of the Intertechelectro - New Generation Group of companies.

18 August 2008

Intertechelectro - New Generation Group of companies participated in “Russia’s Electric Power Industry – 2008” conference

Major “Russia’s Electric Power Industry – 2008” exhibition & conference was arranged in Russia’s capital and demonstrated high interest of Russian and foreign power specialists, equipment & materials manufacturers, financial institutions and mass media. On the last day of the conference, Mr. Eugenie Tsirulnikov, Deputy Director of the Intertechelectro - New Generation Group of companies, presented his report.

15 August 2008

Project & Engineering Center of New Generation LLC finishes the engineering of the 220/10 kV Anna substation to be installed in the Sverdlovsk region

Project & Engineering Center of New Generation LLC incorporated in the Intertechelectro - New Generation Group of companies is involved in the implementation of a large project in the Sverdlovsk region and provides design documentation for the 220/10 kV Anna substation construction.

11 August 2008

Intertechelectro – Turbomontazh LLC registered in Tyumen

In Tyumen, the engineering & construction company Intertechelectro incorporated in the Intertechelectro - New Generation Group of companies registered Intertechelectro – Turbomontazh LLC, a subsidiary company for heat-mechanical equipment installation and maintenance.

01 August 2008

The Intertechelectro - New Generation Group of Companies celebrates the 7th Anniversary

The foundation of Intertechelectro CJSC, a company that paved the way for the development of the entire Group, was a starting point in the history of the Intertechelectro - New Generation Group of companies. Also in 2001, the Russian Government took a far-reaching decision on restructuring the power industry monopoly.