Photo-reports

29 June 2007

Working Visit by M.Sarovin, First Deputy Mayor of Noyabrsk, to the Noyabrsk Combined Cycle Generation Plant Site

S. B. Zemskov, Deputy Director General of <nobr>Intertechelectro-New</nobr> Generation LLC, Noyabrsk CCGP Project Manager, and S. D. Cherkasov, Executive Director of Noyabrsk CCGP LLC, made Deputy Mayor familiar with the plant construction progress at the site.
30 January 2007

Construction Launching Ceremony at Noyabrsk Combined Cycle Generation Plant

On January 30, 2007, the Town of Noyabrsk in <nobr>Yamalo-Nenets</nobr> Autonomous District held a solemn ceremony of launching the construction of Noyabrsk Combined Cycle Generation Plant.
30 January 2007

Meeting Held by V.Khristenko, RF Minister of Industry and Energy, on Energy Deficit Problems at Tyumen Energy Hub

On January 30, 2007, the Administration of Noyabrsk <nobr>(Yamalo-Nenets</nobr> AD) held a meeting dedicated to power supply to Tyumen Energy Hub.
30 January 2007

Press conference of the RF Minister of Industry and Energy V. Khristenko and Chairman of the Board of Directors of <nobr>Intertechelectro-New</nobr> Generation LLC. А. Bikov

On January 30, 2007, the Town of Noyabrsk in <nobr>Yamalo-Nenets</nobr> Autonomous District held a solemn ceremony of launching the construction of Noyabrsk Combined Cycle Generation Plant. It is a project of <nobr>Intertechelectro-New</nobr> Generation LLC for the construction of <nobr>medium-capacity</nobr> power plants in energy deficient regions of Russia.
19 January 2007

Pre-Construction Operations at Noyabrsk CCGP Construction Site

<nobr>Pre-construction</nobr> operations started at the <a href="/projects/Noyabrsk-project/">Noyabrsk CCGP</a> construction site in October 2006.