Photo-reports
11 May 2010
Photo report on the Noyabrsk CCGT power plant site progress
Preoperational testing on the Noyabrsk CCGT power plant.
05 October 2009
Photo report on the Noyabrsk CCGT power plant site progress
26 February 2009
Photo report on the Noyabrsk CCGT power plant site progress
03 February 2009
The first smoke stack installation is launched at the Noyabrsk CCGT power plant
The first smoke stack installation is launched at the Noyabrsk CCGT power plant
29 December 2008
The GT units installation is proceeding at the Noyabrsk CCGT power plant site
The GT units installation is proceeding at the Noyabrsk CCGT power plant site
05 September 2008
The main stage of the Noyabrsk CCGTPP construction
The key stage of Noyabrsk CCGTPP construction: the specialists are mounting the main and auxiliary equipment.
07 August 2008
Works at the Noyabrsk CCPP construction site in progress
30 April 2008
Equipment installation started at the Noyabrsk CCPP site
Construction is about to complete at the Noyabrsk CCPP site. The next stage is the installation of the major and auxiliary equipment and finishing inside the buildings. In 2008, construction workers are expected to complete the installation activities and get ready for the power plant Unit 1 & 2 startup and commissioning.
04 February 2008
The Noyabrsk CCGTPP first steam turbine passes successfully testing at Kaluga Turbine Factory
In the first ten-day period of February the first steam turbine will be dismantled and sent to the Noyabrsk Combined-Cycle Power Plant site. The project for its construction is implemented by Intertechelectro – New Generation Group
09 November 2007
First GE Series PG6581 Gas Turbine Designed for Noyabrsk CCGP Arrived at Kogalym Airport
The first gas turbine designed for Noyabrsk CCGP arrived at the Town of Kogalym by a special flight of Ruslan air liner from St. Petersburg. An almost 100-ton piece of equipment was shipped to the Town of Noyabrsk by a truck train.
01 November 2007
First GE Series PG6581 Gas Turbine Crossed Russian Frontier. It Will Be Installed at Noyabrks CCGP.
A gas turbine and generator weighing 170 tons in total arrived to the Port of St. Petersburg. The equipment designed for Noyabrsk CCGP being constructed by Intertechelectro-New Generation Group of Companies has been supplied from a GE factory in France.
09 Jule 2007
Public Hearing on Environmental Impact Assessment of Noyabrsk Combined Cycle Generation Plant
Researchers of the Tyumen State University Research Laboratory for Ecology and Rational Use of Natural Resources in cooperation with executives of <nobr>Intertechelectro-New</nobr> Generation LLC presented an environmental impact assessment research data on Noyabrsk CCGP.
- 1