Photo-reports

11 May 2010

Photo report on the Noyabrsk CCGT power plant site progress

Preoperational testing on the Noyabrsk CCGT power plant.
03 February 2009

The first smoke stack installation is launched at the Noyabrsk CCGT power plant

The first smoke stack installation is launched at the Noyabrsk CCGT power plant
29 December 2008

The GT units installation is proceeding at the Noyabrsk CCGT power plant site

The GT units installation is proceeding at the Noyabrsk CCGT power plant site
18 September 2008

05 September 2008

The main stage of the Noyabrsk CCGTPP construction

The key stage of Noyabrsk CCGTPP construction: the specialists are mounting the main and auxiliary equipment.
30 April 2008

Equipment installation started at the Noyabrsk CCPP site

Construction is about to complete at the Noyabrsk CCPP site. The next stage is the installation of the major and auxiliary equipment and finishing inside the buildings. In 2008, construction workers are expected to complete the installation activities and get ready for the power plant Unit 1 & 2 startup and commissioning.
04 February 2008

The Noyabrsk CCGTPP first steam turbine passes successfully testing at Kaluga Turbine Factory

In the first ten-day period of February the first steam turbine will be dismantled and sent to the Noyabrsk Combined-Cycle Power Plant site. The project for its construction is implemented by Intertechelectro – New Generation Group
09 November 2007

First GE Series PG6581 Gas Turbine Designed for Noyabrsk CCGP Arrived at Kogalym Airport

The first gas turbine designed for Noyabrsk CCGP arrived at the Town of Kogalym by a special flight of Ruslan air liner from St. Petersburg. An almost 100-ton piece of equipment was shipped to the Town of Noyabrsk by a truck train.
01 November 2007

First GE Series PG6581 Gas Turbine Crossed Russian Frontier. It Will Be Installed at Noyabrks CCGP.

A gas turbine and generator weighing 170 tons in total arrived to the Port of St. Petersburg. The equipment designed for Noyabrsk CCGP being constructed by Intertechelectro-New Generation Group of Companies has been supplied from a GE factory in France.
09 Jule 2007

Public Hearing on Environmental Impact Assessment of Noyabrsk Combined Cycle Generation Plant

Researchers of the Tyumen State University Research Laboratory for Ecology and Rational Use of Natural Resources in cooperation with executives of <nobr>Intertechelectro-New</nobr> Generation LLC presented an environmental impact assessment research data on Noyabrsk CCGP.