Photo-reports

01 October 2013

28 September 2012

Photo report on progress of works on the Kurgan CHPP-2 construction site

Commissioning works at Kurgan HPP-2
22 February 2012

Photo report on progress of works on the Kurgan CHPP-2 construction site

To date the main equipment installation at Kurgan HPP-2 has been completed and commissioning work is in progress
15 October 2011

Photo report on progress of works on the Kurgan CHPP-2 construction site

Commissioning works at Kurgan HPP-2
26 September 2007

Kurgan HPP (Subsidiary of Intertechelectro-New Generation LLC) and PSG—International Signed Contract for Design, Supply and Construction of CCGP at Kurgan on September 26, 2007

PSG-International will operate as the EPC Contractor for Kurgan HPP-2 Construction Project, i.e., will ensure turnkey construction of a combined cycle generation plant.
26 September 2007

First Pile Has Been Driven into Foundations of Main Building of Kurgan HPP-2.

Intertechelectro-New Generation Group of Companies has officially started the construction of a new thermal power plant.
06 September 2007

Kurgan HPP-2 Construction Operations Are Under Way on Schedule

During a month of pre-construction operations, a fertile topsoil layer has been finally removed, security guards have been mobilized and information boards installed, a transformer substation has been connected for temporary power supply purposes, onsite excavation is about to finish, and installation of a temporary heat supply line is underway at the construction site.
01 August 2007

Pre-Construction Operations Started at Kurgan HPP-2 Construction Site

Pre-construction operations are carried out at the construction site of Kurgan HPP-2 preceding the principal construction stage. At present, a fertile soil layer is cut off and removed, and a fence is installed.
20 June 2007

Signature of Agreement on Cooperation and Interaction in Developing and Implementing Investment Program for New Generation Construction Project in Area of Kurgan Region

This Agreement sets out the fundamental principles of interrelations between the Regional Government and <nobr>Intertechelectro-New</nobr> Generation LLC towards successful implementation of the 220MW and 250GCal combined cycle HPP construction at the Town of Kurgan.
05 May 2007

Public Hearings concerning Environmental Impact of Kurgan <nobr>HPP-2</nobr> (Northern), Town of Kurgan

Representatives for <nobr>non-governmental,</nobr> environmental, and veteran organizations, power authorities, energy companies, and mass media were present at the hearings.