Press-centre
Photo-reports
29 December 2008
The GT units installation is proceeding at the Noyabrsk CCGT power plant site
The GT units installation is proceeding at the Noyabrsk CCGT power plant site
05 September 2008
The main stage of the Noyabrsk CCGTPP construction
The key stage of Noyabrsk CCGTPP construction: the specialists are mounting the main and auxiliary equipment.
07 August 2008
Works at the Noyabrsk CCPP construction site in progress
30 April 2008
Equipment installation started at the Noyabrsk CCPP site
Construction is about to complete at the Noyabrsk CCPP site. The next stage is the installation of the major and auxiliary equipment and finishing inside the buildings. In 2008, construction workers are expected to complete the installation activities and get ready for the power plant Unit 1 & 2 startup and commissioning.
13 March 2008
Intertechelectro – New Generation LLC signs the agreement on participation in the ‘Ural Industrial – Ural Polar' Project implementation
The meeting under the chairmanship of Viktor Basargin, Deputy Plenipotentiary of the RF President in the Urals Federal District, was held on March 12 in Yekaterinburg. The meeting participants, among whom there were representatives of the legislative and executive authorities, energy producers and oil-and-gas producing companies, discussed the process of evolvement of the power component of the ‘Ural Industrial – Ural Polar’ Project.
04 February 2008
The Noyabrsk CCGTPP first steam turbine passes successfully testing at Kaluga Turbine Factory
In the first ten-day period of February the first steam turbine will be dismantled and sent to the Noyabrsk Combined-Cycle Power Plant site. The project for its construction is implemented by Intertechelectro – New Generation Group
09 November 2007
First GE Series PG6581 Gas Turbine Designed for Noyabrsk CCGP Arrived at Kogalym Airport
The first gas turbine designed for Noyabrsk CCGP arrived at the Town of Kogalym by a special flight of Ruslan air liner from St. Petersburg. An almost 100-ton piece of equipment was shipped to the Town of Noyabrsk by a truck train.
01 November 2007
First GE Series PG6581 Gas Turbine Crossed Russian Frontier. It Will Be Installed at Noyabrks CCGP.
A gas turbine and generator weighing 170 tons in total arrived to the Port of St. Petersburg. The equipment designed for Noyabrsk CCGP being constructed by Intertechelectro-New Generation Group of Companies has been supplied from a GE factory in France.
26 September 2007
Kurgan HPP (Subsidiary of Intertechelectro-New Generation LLC) and PSG—International Signed Contract for Design, Supply and Construction of CCGP at Kurgan on September 26, 2007
PSG-International will operate as the EPC Contractor for Kurgan HPP-2 Construction Project, i.e., will ensure turnkey construction of a combined cycle generation plant.
26 September 2007
First Pile Has Been Driven into Foundations of Main Building of Kurgan HPP-2.
Intertechelectro-New Generation Group of Companies has officially started the construction of a new thermal power plant.
06 September 2007
Kurgan HPP-2 Construction Operations Are Under Way on Schedule
During a month of pre-construction operations, a fertile topsoil layer has been finally removed, security guards have been mobilized and information boards installed, a transformer substation has been connected for temporary power supply purposes, onsite excavation is about to finish, and installation of a temporary heat supply line is underway at the construction site.
01 August 2007
Pre-Construction Operations Started at Kurgan HPP-2 Construction Site
Pre-construction operations are carried out at the construction site of Kurgan HPP-2 preceding the principal construction stage. At present, a fertile soil layer is cut off and removed, and a fence is installed.
09 Jule 2007
Public Hearing on Environmental Impact Assessment of Noyabrsk Combined Cycle Generation Plant
Researchers of the Tyumen State University Research Laboratory for Ecology and Rational Use of Natural Resources in cooperation with executives of <nobr>Intertechelectro-New</nobr> Generation LLC presented an environmental impact assessment research data on Noyabrsk CCGP.
29 June 2007
Working Visit by M.Sarovin, First Deputy Mayor of Noyabrsk, to the Noyabrsk Combined Cycle Generation Plant Site
S. B. Zemskov, Deputy Director General of <nobr>Intertechelectro-New</nobr> Generation LLC, Noyabrsk CCGP Project Manager, and S. D. Cherkasov, Executive Director of Noyabrsk CCGP LLC, made Deputy Mayor familiar with the plant construction progress at the site.
20 June 2007
Signature of Agreement on Cooperation and Interaction in Developing and Implementing Investment Program for New Generation Construction Project in Area of Kurgan Region
This Agreement sets out the fundamental principles of interrelations between the Regional Government and <nobr>Intertechelectro-New</nobr> Generation LLC towards successful implementation of the 220MW and 250GCal combined cycle HPP construction at the Town of Kurgan.
11 May 2007
Signature of Agreement on Interaction towards Implementation of Activities to Ensure Reliable Power Supplies and Make Provisions for Connection to Power Grids of Consumers from Kurgan Region between Administration of Kurgan Region and OJSC RAO UES Russia involving <nobr>Intertechelectro-New</nobr> Generation LLC
The Agreement provides for the implementation of a list of <nobr>high-priority</nobr> steps towards the construction and renovation of electric power facilities until 2011 in order to prevent a capacity deficit and improve reliability of electric power supplies to consumers of Kurgan Region.