Power generation
News
The Noyabrsk CCGT power plant has attracted financing of the Sberbank of the RF
LLC «Intertechelectro-New Generation» has raised financing of the Sberbank of the RF for implementation of the Noyabrsk CCGT power plant project (124 MW, town of Noyabrsk, Yamalo-Nenets autonomous district). The open credit line amounts to 2,540,000,000.00 rubles.
The first power unit energization is prepared at the Noyabrsk CCGT power plant
The 6 kV and 0.4 kV energization for the auxiliaries is arranged at the Noyabrsk CCGT power plant site in the Yamalo-Nenets autonomous district. Voltage is designated for the 62 MW power unit #1 commissioning works.
Heat is supplied to the Noyabrsk CCGT PP auxiliary building
Further to the main building heat has been supplied to the auxiliary one of the Noyabrsk CCGT PP (construction is performed by the «Intertechelectro-New Generation» group of companies). Under increasing frost in the town of Noyabrsk (Yamal-Nenets autonomous district) both the buildings of the Noyabrsk CCGT PP are heated what allows the workers to continue the equipment installation.
Heat is supplied to the Noyabrsk CCGT PP Main building
The Noyabrsk CCGT PP (Yamal-Nenets autonomous district) main building has now the heating devices installed what allowed supplying heat to the building at the end of October.
The first steam turbine installation works have been launched at the Noyabrsk CCGT PP
The installation works on the first steam turbine have been launched in the main building of the Noyabrsk CCGT PP (Yamal-Nenets autonomous district). In accordance with the schedule, the second steam turbine installation will start one month and a half later.
Integrated switchgear has been installed at the Noyabrsk CCGT PP
At the Noyabrsk CCGT PP constructed by the «Intertechelectro-New Generation» group of companies the Siemens SF6 complex switchgear has been installed.
LLC «Service New Generation» will implement automated process control systems (ACS) at the Noyabrsk CCGT PP
LLC «Service New Generation» which is a company of Group of Companies «Intertechelectro-New Generation» has introduced the automatic process control systems and is going to carry out the commissioning works of Noyabrsk CCGT PP (YaNAD).
Staff meeting on the Noyabrsk CCGT PP construction has been conducted
There was a staff meeting on Noyabrsk CCGT PP construction whish will be the largest one in Yamolo Nenetz Autonomous District. The project realized by Group of Companies «Intertechelectro-New Generation» is at the key stage: the specialists are mounting the main and auxiliary equipment
Installation of gas turbine units began at Noyabrsk CCPP
Gas turbine generators were installed on their foundations at the Noyabrsk CCPP construction site (Yamalo-Nenets Autonomous District). The construction of Noyabrsk CCPP, performed by the Intertechelectro - New Generation Group of companies, entered the next stage: major equipment installation.
Equipment installation started at the Noyabrsk CCPP construction site
Construction is about to complete at the Noyabrsk CCPP construction site. The next stage is the installation of major and auxiliary equipment and building interior finishing. In 2008 the construction workers are expected to complete installation activities and to begin startup & commissioning of the power plant units No. 1 & 2.
The Field Staff Office for Construction of Noyabrsk Combined-Cycle Generating Power Plant holds its meeting
The regular meeting of the Field Staff Office for Noyabrsk Combined-Cycle Power Plant Construction was held in Noyabrsk on January 30.
The foundation for the first gas turbine cemented at the Noyabrsk CCGTPP site
The foundation for the gas turbine of Noyabrsk Combined-Cycle Power Plant, the construction of which is with Intertechelectro – New Generation Group, has been cemented within a day.
The second PG6581 series GE gas turbine unloaded at the Noyabrsk CCGTPP site
The second GE gas turbine, unique by its characteristics, has been delivered to Noyabrsk (YaNAD) by dint of the same way as the first one. All the equipment for two gas turbine units will be delivered in full within a month to the Combined-Cycle Power Plant, which is being constructed by Intertechelectro – New Generation Group.
First GE Series PG6581 Gas Turbine Designed for Noyabrsk CCGP Arrived at Kogalym Airport
The first gas turbine designed for Noyabrsk CCGP arrived at the Town of Kogalym by a special flight of Ruslan air liner from St. Petersburg. An almost
First GE Series PG6581 Gas Turbine Crossed Russian Frontier. It Will Be Installed at Noyabrks CCGP
A gas turbine and generator weighing 170 tons in total arrived to the Port of St. Petersburg. The equipment designed for Noyabrsk CCGP being erected by
Viktor Kazarin, <nobr>Vice-Governor</nobr> of YNAD, Inspected Construction of Noyabrsk CCGP
Viktor Kazarin,
YNAD Governmental Officials Visited Noyabrsk CCGP
Dmitry Feofanov, Director of Energy and Utility Complex Department for YNAD, made a working visit to the construction site of Noyabrsk Combined Cycle Generation Plant.
Noyabrsk Combined Cycle Generation Plant Takes Its Shape
Installation of combined cycle generation plant building frame is currently underway at the construction site of Noyabrsk.
Noyabrsk Combined Cycle Generation Plant Meets All Environmental Requirements
Researchers of the Tyumen State University Research Laboratory for Ecology and Rational Use of Natural Resources in cooperation with the executives of
Public Hearing Was Held at Noyabrsk Concerning Water Supplies to Noyabrsk Combined Cycle Generation Plant
Assessment of Noyabrsk CCGP effects on surface water was carried out by the researchers of the Tyumen State University Research Laboratory for Ecology and Rational Use of Natural Resources.